periodToDateSum

The periodToDateSum function adds the specified measure for a given time granularity (for instance, a quarter) up to a point in time, relative to that period.

Syntax

Copy
periodToDateSum(
    measure, 
    dateTime, 
    period, 
    endDate)

Arguments

measure

The argument must be a field. Null values are omitted from the results. Literal values don't work.

dateTime

The Date dimension over which you're computing PeriodToDate aggregations.

period

The time period across which you're computing the computation. Granularity of YEAR means YearToDate computation, Quarter means QuarterToDate, and so on. Valid granularities include YEAR, QUARTER, MONTH, WEEK, DAY, HOUR, MINUTE, and SECONDS.

endDate

(Optional) The date dimension that you're ending computing periodToDate aggregations. It defaults to now() if omitted.

Example

The following function calculates the week to date sum of fare amount per payment, for the week of 06-30-21. For simplicity in the example, we filtered out only a single payment. 06-30-21 is Wednesday. Insights begins the week on Sundays. In our example, that is 06-27-21.

Copy
periodToDateSum(fare_amount, pickUpDateTime, WEEK, parseDate("06-30-2021", "MM-dd-yyyy")